Our Quarterly Cluster Maintenance has concluded and the cluster is back in service. Highlights from this maintenance window include:

- Slurm upgraded from 23.11.10 to 25.05.7
- VAST and ix storage system upgrades

Thank you for your patience while we perform these important updates to the system.
We are still working to resolve a GPU node configuration issue affecting the following nodes after the Slurm upgrade:

- mems-n0
- gpu-n[28-30]
- ppc-n[0-4]

These nodes should be returned to service tomorrow.